Vincent can propose a spot to RP that works best for integration
Monitor 2: Next to HRS door
Proposed spot is close to where it originally was
Next to new electrical rack on the wall
This should keep the line of site required for the tape station
One suggestion from Elodie is to maybe have a long cable for this probe and have the option to be able to move it closer to the beamline on a temporary stand
Monitor 3: On the roof, attached to shielding where old laser roof access ladder was
This monitor is no longer useful here
Useful to keep monitoring the activated water that goes around the shielding on the opposite wall
RP to propose a location on the opposite wall
Monitor 4: Inside lab
RP to propose a location
Initial suggestion is they would like it similarly placed to how it was before in the center of the wall by EBIS
Monitor 5: New portable monitor
This will have the ability to roam the lab
Just require one place for an outlet and a long enough cable to move it around
Open ventilation portholes to HRS where pipes run through
RP to confirm if these now need to be fenced off since with the new platform this will now be at head height
Next steps:
RP to take some screenshots and propose some locations then Vincent will check with integration if the locations fit
If longer cables are required due to monitors being moved around, this will be up to the RP team to follow up on this