  • MBRD5 progressing according to schedule, only electrical connections to be done

    • They had to re-work the QH cable in one extremity where the insulation is locally damaged. THey are writing a NCR for traceability
  • INFN/ASG will review our reception electrical test and request any modificaiton if needed

  • INFN/ASG is preparing a packing/unpacking procedure
  • 4 new heaters have been produced and qualified to 5 kV instead of 3.1 kV. 8 more heaters are under fabrication.
    • HCMBRDC006-CR000056: accepted
    • HCMBRDC006-CR000057: accepted
    • HCMBRDC006-CR000058: accepted
    • HCMBRDC006-CR000061: NOT accepted (HV test failed)
    • HCMBRDC006-CR000059: accepted
    • HCMBRDC006-CR000060: on hold (minor visual defects)