Status of fabrication

Europe/Zurich

Procurements

  1. Collaring shoes launched August 6th
  2. Ground insulation not yet launched, hoping to have news form supplier mid next week
  3. received heaters, but the usual documents are missing

 

Delivery of magnet 5/recovery 3, confirmed the week after collaboration meeting (September 21st). This friday Stefania goes to ASG for the final check. Missing documents

  1. Way to disassemble and re-assemble
  2. Inspection, in particular electrical testing 

 

NCR (non critical) on the QH wiring of magnet 5

 

Pre-assembly of the first aperture of magnet 6 will start next monday. 

 