ISOLDE Technical Coordination Meeting (LS3)
-
-
14:00
→
14:05
General news - Review of minutes 5mSpeakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN)
- 14:05 → 14:15
-
14:15
→
14:20
IBDRS project update - Work in the primary areas - BTY line @ 2 GeV 5m
- HRS access for cleaning. Someone from the technical team to be present for supporting the activity (moving cables aside).
Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN) -
14:20
→
14:25
RILIS Laboratory upgrade project - Exhaust gas line re-routing - activities update 5mSpeakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
- Resin work complete
- Communication issues with SSP team
- Equipment was put in the area before the resin had the full required time to cure - won't know if any damage caused until equipment (if ever) is moved to see below
- Communication issues with SSP team
- Next week shoring at HRS entry
- Week after installation of shielding on RILIS platform
- shoring to be removed on Friday 13th, the same week of the installation
- Simon has prepared a couple slides to show at the next IEFC prep meeting on Nov 4th for final approval of vac pipes ECR
- Safety incident below platform - as discussed in safety section
- Resin work complete
-
14:25
→
14:35
Machine related activities in the experimental hall 10mSpeakers: Erwin Siesling (CERN), Simon Mataguez (CERN)
FEs / HT Boris tube tests:
- A.P. Bernardes request: Consignation HT GPS and HRS - done and in the ICR
- YHRS.QP30-NEG issue (short to ground at patch, cable or in the machine?) - to follow up -> S. Marzari
Platform EPC / vacuum:
- HW tests ongoing: M. Lozano / S. Mataguez
- Consignation on the rack RY02=170 crate rISO-ISEG1 which concerns the sectors HRS10, 20, 30 & 40 in the view of a decabling campaign for the obsolete cables passing from the HRS zone along the RILIS lab wall can be taken off again.
- Limited time for HW tests: (end) Nov rerouting of the (RILIS related) vacuum exhaust tubes - no VSC til May '27.
REX/HIE ISOLDE:- REX/HIE LINAC:
- On the list: replacement prim. pumps CMs, backing & roughing lines - Oct/Nov (after LHC LS high peak work).
- Ongoing: Modification of the chamber of the XL9GP Quad. Chamber to be back in the machine next summer latest.
- Additional NEG pump is to be added onto the XLN2 DBox: After re-installation end of '27 - Replacement of the 9 GAP structure vacuum seal: Response from the RF group (S. Ramberger):
We would in a first step want to try to retighten the bolts.
Remark E.S.: tests can only be done after the vacuum and water (when RF to the structure) are back (resp. May, July '27) and RF amplifiers are installed.
- Our analysis showed that we might not have applied the maximum torque that is acceptable.
- Only if the structure is still not leak tight, we would open it, verify the exact sealing dimensions and replace the seal with the one that we have available.
- If it would still not be leak tight, we would manufacture a new seal according to the measured sealing dimensions.
- we need to make sure that we can power the 9GAP after each action for testing. - REX Low E development:
- Replacement of the leaking REX mass slits actuator for a bellow type one using a HIE type actuator under discussion and to be scheduled with the upcoming BI works on the HEBT lines which will be liberated during the exchange in the HEBT lines for the newer version. Under discussion/investigation M. Nieto/A. Rodriguez/E. Siesling/F. Wenander - REXTRAP innner structure work ongoing in 179. Clear traces of discharger (J. Schoonwater, F. Wenander).


- BI work in the HEBT zone using the allocated work space between XT02 and 03: To start after PUMA / RC6 related work has finsihed - news M. Nieto?
Separator zones HRS & GPS:
- Field regulation rack and CAO + Tapestation racks positions identified but demand for extra rack space: To investigate with F. Wenander if the REX gas bottle spot can be canged in order to house a (small) rack. - action E. Siesling.
- PLAN (14522) created for the field regulation installation works (M. Torre / E. Siesling).
- DCCT boxes (M. Marreiros EN/EL, D. Giloteaux TE/MSC, M. Torre TE/MSC) for HRS90 & 60 accurate DC current measurement for the field regulation systems positions to be defined/validated by the take holders (S. Marzari, K, Chrysalidis, M. Duraffourg, V. Barozier).
Infrastructure / 197 BTY & Separators Power supplies consolidation:
- 197 installation works: See comments J. Vollaire
- Chilled water / AC in 508 and for the 170 HVAC system situation update? Flexibles to be lifted onto the 170 roof. (A. Fournier).
Fume cupboards GLM/GHM:
- New chemical fumecupboard in old ICR: - cable tray in the way of a free duct passage through the false floor (difficult to solve). Status? (N. Szczepanik-Scislo, A. Fournier, V. Barozier)
Fiber Optics work / ISOLDE timing upgrade:
- 2nd phase of the White Rabbit fiber optics installation (N. Simic) postponed to 14/06/27 - 25/06/27
- Timing upgrade of the full facility discussed in regular meetings (E. PIselli, L. Nies, G.P. Di Giovanni, Controls groups). This includes the CAO switching, REX timing upgarde, MR-Tof/PUMA, beamgate inclusion). Full new ISOLDE timing versus partial upgrade and patch to work with existing timing systems: conclusion LS3 to migrate to full White Rabbit.
- ECR for beamgates will be rewritten (L. Nies). New beamgates ower supplies will need space. Agreed is to move the 3 FEC's in rack 03 in the OICR - equipment owners been contacted (L. Nies). Ongoing.
Other:
- evacuation of the buildings in the frame of the installation of the large standing crane for IBDRS moved to 18th Nov (G. Cnudde). Confirmation will be send out to the ISO House group
-
14:35
→
14:40
Experiments related activities in the experimental hall 5mSpeakers: Hanne Heylen (CERN), Oscar Fjeld (CERN)
Ongoing/planned
- ISOLTRAP AC cabling (Erwin)
- COLARIS
- Meeting for removal of concrete pillars -> Erwin
- COLLAPS: continue working on ion source in 508 and 170
- CRIS:
- Cleaning week: first 2 weeks of November
- GLM:
- This week: Juliana's team will place some experimental equiment temporarily
- Started with this last Friday already, before agreed moment for curing of equipment
- This week: Juliana's team will place some experimental equiment temporarily
- GHM:
- Guilherme is around second week of November -> inquired about vacuum valve which needs replacement
-
14:40
→
14:45
Experiments related activities in the experimental hall 5mSpeaker: Erwin Siesling (CERN)
ISOLTRAP:
- Re-installation of infrastructure and equipment ongoing (A. Jaries)
COLLAPS/CRIS platform:
- Meeting held in situ with Tranport and SCE (Y. Seraphin & team, S. D'Armancourt) for the removal of the concrete structure:
First stage:
- removal as much as possible of the equipment / mirror boxes, etc.
- scaffolding needed for transport to prepare for the hanlding of the large beam (8m, 6 ton). - action E. Siesling (contact Ouvaroff)
- the large concrete beam needs to be cut up in 3 pieces in the ISOLDE hall (PUMA area)
- removal of the two 80x80 small blocks
- timeline to agree on with RILIS and other activities but asap
second stage:
- removal of the scaffodling followed by removal of the services on the tall concrete blocks (RP monitors, cable trays, AC distribution)
- removal of the tall concrete blocks
-timeline: before the end of the year
PUMA:
- EN/EL AC cable work VIC planned for Friday: installation to follow soon by new contractor (M. Parodi, P. Gallay EN/EL).
- Re-installation of infrastructure and equipment ongoing (A. Jaries)
-
14:45
→
14:55
Mechanical Workshop and other support requests 10mSpeaker: Oscar Fjeld (CERN)
Last week:
- ISOLDE sign - finalising, offer recieved and approved.
-
Rex Trap - missing aluminium support for the quadrupole doublet machined and completed.

- LHe - support
New request:
-
ISOLTRAP - reduce the ground electrode diameter from 38.5 to 38 mm and restore the rounded edges.
-
COLLAPS - remake the slide in bronze and add grease-retaining grooves to existing parts
-
GLM - cut an opening in an aluminium frame and cut a PVC pipe to length.
-
14:55
→
15:00
Planned visits and AOBs 5mSpeaker: Hanne Heylen (CERN)
-