Clarification of RILIS 3D model

→ Europe/Zurich
CERN

CERN

Zoom Meeting ID
68710838255
Host
Laura Lambert
Useful links
Join via phone
Zoom URL
    • 15:30 → 16:30
      Clarification of RILIS 3D model 1h

      A few points to cover:

      • Validation of roof reinforcements
      • Ports through the sandwich panels (EBIS etc)
      • Reinforcements for boris tube
      • Update the I-beams underneath around ISCOOL area
      • Door entry height updated
      Speakers: Julien Prosic, Laura Lambert (CERN), Lukas Nies (CERN), Severin D'Armancourt (CERN), Tiago Nico (CERN), Vincent Barozier
      • Validation of roof reinforcements
        • interference between boris tube and roof reinforcements - reinforcements to be adjusted by Vincent
        • Lukas to update the rack model insulating feet so feet are in correct place
        • Vincent to adjust the position of the transformer to fit the reinforcements and the beams accordingly
        • Vincent to provide location and dimensions of FC cage to Severin
      • Ports through the sandwich panels (EBIS etc)
        • EBIS is tight but OK - all within one panel
        • ventilation ports x 2 - to be cut on site
          • one from entry sas floor to lab needs to be laser tight - how? to check with CV and LSO
        • cable port - to be cut on site
      • Back panel around HRS laser launch and door - to be cut on site
      • Reinforcements for boris tube
        • Correct now in 3D and in manfacturing
      • Update the I-beams underneath around ISCOOL area
        • OK now
      • Door entry height
        • Tiago to provide this to Vincent once contractor has this updated for integration (beam to be cut)
      • All walking surface inside the FC needs to be updated to be a smooth surface
        • Severin needs to include more reinforcement beams if we want this
        • Will make the whole platform smooth/flat for ease of execution
      • Boris tube will need to be installed before the ceiling otherwise there won't be the clearance
        • Ceiling panel will be cut on-site to adapt to the tube, best would be to have a panel cut in 2 with two semicircles and close it around the tube
      • CV to update some pipe routing on roof still
      • Cable tray in back HRS wall of ISCOOL needs to be shifted down in order to instal reinforcements for boris tube (so before week 47) 
      • Tiago to ensure that all drawings he provides to Vincent from his contractor are the good version to work with
      • Between panels - do we need to put any extra mastic or silicone for better airtightness? Follow up with CV/Kati