- The final HT tube is approximately 4.3 m long and 200 kg. For the final assembly, polyurethane must be poured at both ends with the tube vertical, requiring the tube to be turned between pours. Drying is expected to take approximately one day per side.
- Building 927 was identified as the preferred location for assembly and polyurethane filling. It provides crane access, sufficient height, and more flexibility than Building 867, while likely avoiding the need for scaffolding.
- The tube can be secured vertically to the existing handrail/structure in Building 927, similar to previous work on the ISOLDE beam-dump mock-up. An additional safety restraint should be provided.
- Suitable lifting/handling interfaces are required for turning the tube safely. Lifting rings are available on one end; the opposite end may require a sling arrangement with a mechanical stop to prevent slipping.
- The tube ends and smooth external surfaces must be protected during handling. Thick rubber underneath the tube and additional temporary surface protection were proposed.
- External flanges do not necessarily need to be installed before polyurethane filling and could be mounted afterwards to simplify handling.
- For the final installation, placing scaffolding on the second-floor/roof level rather than the first floor could simplify access. The stated roof capacity is 500 kg/m², but the scaffolding arrangement still needs confirmation.
- The central structural beam cannot be removed. Previous handling studies indicate that the main limitation is likely the diameter of the concrete opening rather than the surrounding roof opening.
- The concrete drilling is planned for Friday of the following week. The currently foreseen 250 mm hole diameter may need to be increased based on the final tube geometry and handling requirements.
Action items
- Lukas Nies / Timo: Check the latest 3D model and determine the required concrete opening diameter before drilling.
- Lukas Nies: Communicate the finalized drilling/core diameter to Jon Musitu Heras.
- Jon Musitu Heras: Recheck the installation/rotation study once the final hole diameter is confirmed.
- Stefano Marzari / Timo: Confirm the lifting interfaces and thread specifications required for the lifting rings and opposite-end handling.
- Stefano Marzari: Define/provide suitable protection for the tube ends and external surfaces during handling.
- Maria Perez Ornedo / handling team: Confirm an appropriate anti-slip lifting arrangement/mechanical stop for safely rotating the tube