ISOLDE Technical Coordination Meeting (LS3)
-
-
14:00
→
14:05
General news - Review of minutes 5m
https://proton-journey.web.cern.ch/
Speakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN) -
14:05
→
14:15
Safety matters 10mSpeakers: Andreas Herty (CERN), Hanne Heylen (CERN), James Devine (CERN), Joachim Vollaire (CERN)
-
14:15
→
14:20
IBDRS project update - Work in the primary areas - BTY line @ 2 GeV 5m
PS Booster side:
- Reception of civil engineering work in the PS Booster
- Painting planned next week
- Preparation of refurbished magnets installation
- Marking of floor for new supports, displaced girders and new stoppers location
- Installation of ceiling mounted rail planned in January (EN-EL and EN-AA interventions required to relocated services).ISOLDE side:
- VIC for 9 m long carrotage. Activity on hold for endoscope inspection to confirm routing of services (vacuum exhaust line) before proceeding.
- CMAC visit last week.IBDRS:
- Fixed crane was installed Monday 23/11 early morning.
- EN-CV will finalize the insulation of temporay flexible pipes for the chilled water this week (weather permitting) and proceed with the pipes filling.
- Discussion ongoing to plan the re-installation of the pipes along building 170 (different planning scenarios with the installation of a dedicated fixed crane for EN-CV).Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN) -
14:20
→
14:25
RILIS Laboratory upgrade project - Exhaust gas line re-routing - activities update 5mSpeakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
- Shielding blocks on backwall have been painted
- Boris tube support beams installed and core drilling through main platform done
- CAREFUL if access is required on the platform, as there is a hole in the platform. A rubber mat is covering it with a warning sign overtop.
- Vac pipe
- cutting started yesterday with some good progress
- require more scaffolding in HRS - planned for Thurs
- Cables require moving in order to access the pipe
*NOTE* If an authorized person requires access to the platform, please ensure that the access-limiting chain at the bottom of the stairs is closed again immediately after access.
-
14:25
→
14:30
Machine related activities in the experimental hall 5mSpeakers: Erwin Siesling (CERN), Simon Mataguez (CERN)
Platform EPC / HW tests:
- Final tests done before vacuum was stopped on the 16th Nov – reporting Miguel
- Vacuum expected back May ‘27
- Rerouting of the vacuum exhaust lines ongoing: See RILIS reporting.
REX/HIE ISOLDE:- Removal of old cables and stripping of the old amplifiers in the REX RF room ongoing: Giampaolo Piccinini.
- Solid state amplifiers and digital LLRF activities ongoing.
- REX Low E development:
New Mass-slits system at the REX Separator concept being worked on (M. Nieto) - news?
- REXTRAP inner structure work ongoing in 179. (J. Schoonwater, F. Wenander).
- HIE ISOLDE related BI work:
New strategy instrumentation upgrade:
- installation 7 newest actuators + 1 spare (instead of only 3 and strategic reshufflling)
- replacement of 3 slit plates by vertical square collimator slits
- recalibration 10 diagnostic boxes
Follow-up meeting Tues 17 Nov (S. Mataguez, w. Andreazza, (M. Nieto excused), et all.) – reporting Simon
Simon will group all BI work during LS3 including the reversed engineering for drawings and future spares of the GPS and HRS SEMGRIDS and SLITS systems
HIE Cryo systems:
- Design and integration work for the bypass valve box, evaporator and recuperation line in view of the full integration of the 2kL LHe dewar is ongoing (L. Stewart, T, Dupont TE-CRG, V. Barozier)
- Installation will be done in the cause of 2027 with the aim to have all ready for commissioning together with the cryo plant end '27/start up '28
Separator zones HRS & GPS/HRS entrance area:
- Old field measurements test cables can be recuperated (RP check done) – action M. Torre
- Old Tapestation rack has been transported in front of the SAS door – to be checked by RP then recuperated by Ricardo
- Installation new cable trays under RILIS - any news?
- Supporting beams for the ceiling installed and core drilling was done for the ISCOOL Boris tube – RILIS report?
Infrastructure / 197 BTY / Separators Power supplies consolidation:
- 197 installation works ongoing – Meeting held: adaptation floor grids (Severin, asap), Power convertors installation (Jan? ’27), AC (April ’27) and DC cabling (Aug ’27): See comments J. Vollaire
- Chilled water / AC in 508 and for the 170 HVAC system situation update?
Fume cupboards GLM/GHM:
- New chemical fumecupboard in old ICR: - possible to route the duct through the ceiling along the wall. Small modification identified: earth connections and cable tray as well as displacement of items on the 197 wall – modifications preferably before cabling campaign (AC) starts to use the resources from CV when available.
Fiber Optics work / ISOLDE timing upgrade:
- ISOLDE Central Timing Renovation - Functional and operational requirements being written by J. Sanchez
Regular meetings (L. Nies, E. Piselli, G.P. Di Giovanni, Controls groups). This includes the CAO switching, REX timing upgarde, MR-Tof/PUMA, beamgate cons. - Timing needs for the new digital LLRF system (fiber – White Rabbit) will be identified and discussed with Daniel Valuch: Lukas Nies
Ioan Kozsar, Evangelia Gousiou BE-CEM, Grzegorz Kruk BE-CSS been made aware (G.P. Di Giovanni)
GHM line:
- The end valve to be turned so that there is no conflict with future experiment installation- not yet done (J. Somoza)
New beamgates:
- For the new beamgates system it would be best to have a multipin cable (NE48 or 64) from the ICR 508 to the racks in the old control room in 197. With Didier Chapuis we try to get this onto an existing DIC for the modifications on the access keys control panel (for which several new cables need to be pulled).
Ticket nr RQF2629435. Hopefully we manage. Lukas Nies added to the watch list of the ticket – please identify how many pins and if the OK comes from EN/EL to modify the exact staring and end point (508-1-002 to 197-R-001 rack position, etc.)
- 14:30 → 14:35
-
14:35
→
14:45
Experiments related activities in the experimental hall 10mSpeaker: Erwin Siesling (CERN)
Experiments related activities in the experimental hall:
ISOLTRAP:
- Re-installation of infrastructure and equipment ongoing (A. Jaries)
- AC cabling still to be discussed with EN/EL P. Gallay and new contractor? (L. Nies, A. Jaries, E. Siesling) - news?
- Crane lock-out wk47: dewar handling planned for Fri 20 Nov – worked out OK
- The 170 parking was free on Mon 23 Nov again, just in time for the dewar filling for ISOLTRAP (parking was blocked due to the rising of the IBDRS large crane)
COLLAPS/CRIS platform:
- Scaffolding was installed and validated on Wednesday 18 Nov (Ouvaroff, E. Siesling)
- Removal of the remaining laser tubes and structures on the main long concrete beam Wedn / Thursd (Erwin/Oscar/Tim)
- Thursday: PUMA zone prepared and protected for storing and cutting of the concrete beam
- Transport intervention on Friday-morning after deconsignation of the crane:
- The large concrete beam was removed + 2 small 80x80cm blocks (transport, F. Schneiter)
- All remaining supports and garde-corps were removed once on the floor (O. Fjeld, E. Siesling)
- As of Mon 23 Nov preparations (SAS) and cutting up/core drilling of the concrete beam in 3 pieces in the ISOLDE hall (PUMA area, wet cutting with plastic SAS) (SCE, S. D'Armancourt) – ongoing
- two concrete blocks (80x80), support structures, ladder (to be recuperated) in front of the SAS as well as the garde-corps along the Jura side wall to be checked by RP. – request send out- Removal of the scaffolding foreseen Wedn 2 Dec (OK with other activities)
- second stage- before the end of the year:
- removal of the services on the tall concrete blocks (E-net sockets done, RP monitors done. To do: cable trays, AC distribution discussed with P. Gallay EN/EL - ticket probably enough
- removal of the tall concrete blocks
- Design new platform with SCE (S. D'Armancourt - contractor). Follow-up ICL meetings. Organizational: Lead by H. Heylen.
Meeting with SCE / Severin / Vincent on design resources, etc. was held Thursd 19 Nov:
- Existing design will be taken up by the designer/contractor for a first price estimation of the new platform and labs underneath – before the end of the year
- Existing design to be finalized and validated by January to start design of the metal structures, etc.
- Metal structures and Labs design to be made available for CV to integrate the services (March/April?)
- Delivery metal structure in Spring ’27 – installation of the infrastructure (CV) June? + installation of the infrastructure and experiments equipment
PUMA:
- AC cable installation started Tues 17 Nov (from 199 along the walls in the HIE side of the hall to a new LC7 AC cabinet)
- Large part of the cables installation done, some missing. Another intervention to be planned when material has arrived – one day of crane outage for work at heights (date tbc)
- AUG control cable to be pulled from the PUMA AC cabinet (LR7): most probably this week -> to be coordinated with COLLARIS scaffolding dismounting
-
14:45
→
14:55
Mechanical Workshop and other support requests 10mSpeaker: Oscar Fjeld (CERN)
-
14:55
→
15:00
Planned visits and AOBs 5mSpeaker: Hanne Heylen (CERN)
-