ISOLDE Technical Coordination Meeting (LS3)

→ Europe/Zurich
508/1-001 (CERN)

508/1-001

CERN

20
Show room on map
Zoom Meeting ID
62093336977
Host
Joachim Vollaire
Useful links
Join via phone
Zoom URL
    • 14:00 → 14:05
      General news - Review of minutes 5m

      https://proton-journey.web.cern.ch/

      Speakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN)
    • 14:05 → 14:15
      Safety matters 10m
      Speakers: Andreas Herty (CERN), Hanne Heylen (CERN), James Devine (CERN), Joachim Vollaire (CERN)
    • 14:15 → 14:20
      IBDRS project update - Work in the primary areas - BTY line @ 2 GeV 5m

      PS Booster side:
      - Reception of civil engineering work in the PS Booster
      - Painting planned next week
      - Preparation of refurbished magnets installation
      - Marking of floor for new supports, displaced girders and new stoppers location
      - Installation of ceiling mounted rail planned in January (EN-EL and EN-AA interventions required to relocated services).

      ISOLDE side:
      - VIC for 9 m long carrotage. Activity on hold for endoscope inspection to confirm routing of services (vacuum exhaust line) before proceeding.
      - CMAC visit last week.

      IBDRS:
      - Fixed crane was installed Monday 23/11 early morning.
      - EN-CV will finalize the insulation of temporay flexible pipes for the chilled water this week (weather permitting) and proceed with the pipes filling.
      - Discussion ongoing to plan the re-installation of the pipes along building 170 (different planning scenarios with the installation of a dedicated fixed crane for EN-CV).

      Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN)
    • 14:20 → 14:25
      RILIS Laboratory upgrade project - Exhaust gas line re-routing - activities update 5m
      Speakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
      • Shielding blocks on backwall have been painted
      • Boris tube support beams installed and core drilling through main platform done
        • CAREFUL if access is required on the platform, as there is a hole in the platform. A rubber mat is covering it with a warning sign overtop.
      • Vac pipe
        • cutting started yesterday with some good progress
        • require more scaffolding in HRS - planned for Thurs
        • Cables require moving in order to access the pipe

       

      *NOTE* If an authorized person requires access to the platform, please ensure that the access-limiting chain at the bottom of the stairs is closed again immediately after access.

    • 14:45 → 14:55
      Mechanical Workshop and other support requests 10m
      Speaker: Oscar Fjeld (CERN)
    • 14:55 → 15:00
      Planned visits and AOBs 5m
      Speaker: Hanne Heylen (CERN)