Thermosiphon meeting

→ Europe/Zurich
298/1-003 (CERN)

298/1-003

CERN

10
Show room on map
Michele Battistin (CERN)
    • 14:00 → 14:10
      Planning 10m
      Speaker: Jose Antonio Botelho Direito (CERN)
      Slides
    • 14:10 → 14:20
      Budget situation 10m
      - offer for the brine skid insulation (Daniel) - offer for the balcony unit insulation (Daniel) - offer for the brine flowmeter (Pierre) - cost to completion estimation for the scaffolding (Daniel) - cost of the chiller(s) roof - cost of the condenser roof
      Speaker: Jose Antonio Botelho Direito (CERN)
      Slides
    • 14:20 → 14:30
      Urgent matters 10m
      - installation of the platform for balcony unit transport - diesel power installation: EL to present solution to ATLAS - Compensators supply and installation
    • 14:30 → 14:40
      Document database update 10m
      Speaker: Alexander Bitadze (University of Glasgow (GB))
    • 14:40 → 14:50
      Water circuit - Pipe + pump skid 10m
      - Pump skid done: instrumentation to be installed - pipe installation waiting for end of brine pipe + water skid installation
      Speaker: Stefano Moccia (CERN)
    • 14:50 → 15:00
      Chiller - J&E Hall 10m
      - status of the connections
      Speaker: Olivier Crespo-Lopez (CERN)
    • 15:00 → 15:10
      Brine skid + piping 10m
      - brine skid transport (Cyrill) - brine piping installation (Daniel) - brine diaphragm flowmeter (Pierre)
      Speakers: Cyril Degeorge (I), Daniel Lefils (CERN), Pierre Bonneau (CERN)
    • 15:10 → 15:20
      C3F8 Condenser Installation 10m
      - Condenser supply: pipe support problem (Enrico) - Mechanical installations around the condenser (Pierre) - Degassing system (Cyrill + Pierre)
      Speakers: Cyril Degeorge (I), Dr Enrico Da Riva (CERN)
    • 15:20 → 15:30
      C3F8 pipe installation update 10m
      - Balcony-compressor room part: Didier pipe advancement (Daniel) - DN50 compensator replacement (Daniel)
      Speaker: Daniel Lefils (CERN)
    • 15:30 → 15:40
      TS electrical cupboards construction advancement 10m
      - USA12 cupboards construction status (Florian) - delivery time for the power cubicle form CCM (Olivier)
      Speaker: Florian Corbaz (CERN)
    • 15:40 → 15:50
      Instrumentation 10m
      Speaker: Pierre Bonneau (CERN)
    • 15:50 → 16:00
      USA15 "balcony" assembly status 10m
      - retention bound installation (Cyril) - Skids installation in USA15: transport problems (Olivier) - Installation planning (Olivier)
      Speakers: Cyril Degeorge (I), Pierre Bonneau (CERN)
    • 16:00 → 16:10
      Electrical Power Supply and Cabling 10m
      - Diesel power supply status. - new version of the Electrical requirements document (Jose) - HP connection EN/EL: advancement status (Olivier) - Jan: LP + instrumentation connection: Sergei Malukov advancement status. (Jan)
      Speakers: Daniel Lefils (CERN), Wieslaw Iwanski (CERN)
    • 16:10 → 16:20
      Control 10m
      Speakers: Lukasz Zwalinski (CERN), Stephane Berry (CERN)
    • 16:20 → 16:30
      Safety file 10m
      Speaker: Jose Antonio Botelho Direito (CERN)
    • 16:30 → 16:40
      Commissioning procedures 10m
      Speaker: Jose Antonio Botelho Direito (CERN)
    • 16:40 → 16:50
      Any Other Business 10m