- offer for the brine skid insulation (Daniel)
- offer for the balcony unit insulation (Daniel)
- offer for the brine flowmeter (Pierre)
- cost to completion estimation for the scaffolding (Daniel)
- cost of the chiller(s) roof
- cost of the condenser roof
Speaker:
Jose Antonio Botelho Direito(CERN)
Slides
14:20
→
14:30
Urgent matters10m
- installation of the platform for balcony unit transport
- diesel power installation: EL to present solution to ATLAS
- Compensators supply and installation
14:30
→
14:40
Document database update10m
Speaker:
Alexander Bitadze(University of Glasgow (GB))
14:40
→
14:50
Water circuit - Pipe + pump skid10m
- Pump skid done: instrumentation to be installed
- pipe installation waiting for end of brine pipe + water skid installation
TS electrical cupboards construction advancement10m
- USA12 cupboards construction status (Florian)
- delivery time for the power cubicle form CCM (Olivier)
Speaker:
Florian Corbaz(CERN)
15:40
→
15:50
Instrumentation10m
Speaker:
Pierre Bonneau(CERN)
15:50
→
16:00
USA15 "balcony" assembly status10m
- retention bound installation (Cyril)
- Skids installation in USA15: transport problems (Olivier)
- Installation planning (Olivier)
Speakers:
Cyril Degeorge(I), Pierre Bonneau(CERN)
16:00
→
16:10
Electrical Power Supply and Cabling10m
- Diesel power supply status.
- new version of the Electrical requirements document (Jose)
- HP connection EN/EL: advancement status (Olivier)
- Jan: LP + instrumentation connection: Sergei Malukov advancement status. (Jan)
Speakers: