CMS LS1 WPA meeting to install RE+4 gas services on YE+3
→
Europe/Zurich
530/R-030 - BE-EA Conference Room (CERN)
,
Key dates:
- Cut floor in YE+3 towers X1 Far: 18/02
- Install RE+4 gas rack in tower: 19/02
- Install RE+4 gas pipes in closed ECap config: 27/02 for 7 days
- Install RE+4 gas pipes in open ECap config: 19/03 for 10 days
Total duration for installation of pipes: 17 working days in time window [27/02 ; 02/04]
Action list:
Anton: 1- Design BP protection to be used during pipes installation
2- Request resources from MAF for cutting holes in tower floor
3- Prepare hot work request, IS37….
4- Clarify origin and routing of gas supply to new RE+4 rack
5- Define position of holes in floor
Wojciech:
1- Provide foot print of rack
There are minutes attached to this event.
Show them.
The agenda of this meeting is empty