CMS LS1 WPA meeting to Install the monorail for YE-3

Europe/Zurich
530/R-030 - BE-EA Conference Room (CERN)

530/R-030 - BE-EA Conference Room

CERN

35
Show room on map
Hay David, Martin Gastal
Description
This meeting is designed to assess the risks associated with the installation of the monorail for YE-3
ACT request
Monorail guides
Photo 1
Photo 2
Photo 3
Participants
  • David Hay
  • Eric Dugue
  • Maf Alidra
  • Martin Gastal
  • Michel Arnaud
  • Pascal Petiot



Key dates:
  1. Modify metallic structure : 27/02
  2. Reinforce metallic structure : 27/02
  3. Install Monorails + survey : 28/02
Total duration for installation : 2 (3) working days in time window [27/02 ; 28/02]

Action list:
Pascal:
1- Modify Metallic structure to include TIG welding.
2  Request and prepare Fire permit, IS37
3- Supervise & declare RP metalic dust and waste management.
Eric
1- Provide lifting and handling support. 
Tech Coordination
1 Locate the owner of the fiber optics connection box and arrange for temporary removal during welding process.


 

There are minutes attached to this event. Show them.