The activities to be carried out in the WP will require 1 cherry picker per end
Drainage scheme is being reviewed by P Tropea and will be announced at upcoming TC meetings
The work sequence will start with 3 days of diagnostics of the LV problems encountered on YE+1. The start date for that activity is Thu 04/04.
Action:
Victor: Take course to work in SX5 buffer area
Victor: Keep M Gastal/D Hay informed on decision to carry out removal / re-installation of PPanels.
Martin: Check with EE/ES whether the removal / re-installation of PPanels can be done in May.
There are minutes attached to this event.