29–31 Oct 2013
Centre de Convention, Archamps
Europe/Zurich timezone

HL-LHC: How to achieve Upgrade Scenario 1 goals in the LHC? (20' + 10')

30 Oct 2013, 10:30
30m
Centre de Convention, Archamps

Centre de Convention, Archamps

Domaine de Chosal Archamps Technopole 74160 Archamps

Speaker

Oliver Bruning (CERN)

Description

Abstract: The presentation discusses the options for maximizing the performance reach of a limited HL-LHC upgrade scenario and for reaching the performance goals of the Upgrade Scenario 1 based on Performance Improving Consolidation (PIC) (e.g. new triplet magnets) and only moderate upgrade implementations (e.g. Long Range Beam-Beam Wire compensators and Higher Harmonic RF system but no Crab Cavity system). The presentation will summarize the required key beam parameters and performance issues (e.g. required machine efficiency and run scheduling), discuss the cost and calendar implications for the Upgrade Scenario 1 option and discuss the trade-off between different upgrade options (e.g. Long Range Beam-Beam Wire compensators and Higher Harmonic RF system).

Presentation materials