- DAY 1 - 26/11/2013: on-shore station
- requisites for Phase 1 and Phase 2:
- off-/on- shore dependencies (bandwidth vs throughtput)
- networking structure
- logistics
- requisites for PPM-DU.
- DAY 2 - 27/11/2013: DAQ Part I
- DAQ for PPM-DU:
- heritage from PPM-DOM
- Data format, data aggregation, data selection and storaging for PPM-DU
- DAQ for Phase 1/ Phase 2:
- Basic ingredients: data formats, slow control protocol
- State Machine
- Control Units and Data Base Interface
- DAY 3 - 28/11/2013: DAQ Part II
- DAQ for Phase 1/ Phase 2:
- Data Queue and Data Filter
- quasi online analysis
- data storage.
- Test-bed / test-bench
- Planning
The above agenda could be subject to changes
Any way the general plan is to start not before 10:30 on Tue the 26th and conclude not after 17:30 on Thu the 28th.
-----