- D2.1 ToC 24/7 (now no longer needed due to v15 of DoW)
- D4.1 version 1 to review 31/7
CALENDAR QUERIES:
1) Because of our 45 day deliverable limit, and our final
review, there are two extra months on the ISSeG calendar,
these will be unfunded by the EU. How do we deal with this?
[FH: deliverables will have to be dealt with before or
unfunded, final EU review will be funded by partners.]
2) There are 5 deliverables with M24 deadlines, should
we stagger these and move some deadlines to earlier months?
[FH: will have to be dealt with before or unfunded.]
3) Concerning Christmas 2007, many deliverables run into
this Christmas break, how do we resolve this? [FH: three
possibilities, advance a little bit the deadlines, shorten
the review period or ask EC for a bit of delay.]