The installation of the various LSS is a challenge in the compressed schedule. The
installation scenarios describing the sequences presently planned will be discussed
and potential problematic areas will be highlighted. The particular case of sector 7-
8 where the LSS elements will be installed before the QRL line is completely
terminated will be used as an example of a ‘rapid’ installation scheme to illustrate
how resources are used. The consequences of possible shortcuts will be also
mentioned.