Conveners
Session 6 - Effects of the compressed Schedule on the Installation
- Thomas (Chairman) Pettersson (TS-CSE)
- Felix (Scientific Secretary) Rodriguez Mateos (TS-HDO)
-
Dr Sylvain Weisz (CERN)19/01/2005, 14:00Effect of the compressed Schedule on the InstallationThe impact of the QRL delay on the schedule will be discussed. A number of activities will have to be executed in parallel. A compressed schedule needs to be compatible with the resources available in the various groups involved. The manufacturing limitations and the possibilities to provide the required equipment at the required dates may also lead to dangerous shortcuts. The...Go to contribution page
-
Mr Samy Chemli (CERN)19/01/2005, 14:40Effect of the compressed Schedule on the InstallationThe precise knowledge of what needs to be installed is clearly a prerequisite to the fast schedule feasibility. The talk will give an overview on the expected configuration of the as-should-be-built LHC (v6.5), the LHC reference database and the tools available to access it. The areas where information is still missing or where the integration is not finalized will be listed and...Go to contribution page
-
MARIA SONIA BARTOLOME JIMENEZ (CERN)19/01/2005, 14:55Effect of the compressed Schedule on the InstallationThe installation of the various LSS is a challenge in the compressed schedule. The installation scenarios describing the sequences presently planned will be discussed and potential problematic areas will be highlighted. The particular case of sector 7- 8 where the LSS elements will be installed before the QRL line is completely terminated will be used as an example of a ‘rapid’...Go to contribution page
-
Dr Vinod Chohan (CERN)19/01/2005, 15:40Effect of the compressed Schedule on the InstallationThe Testing Facility in SM18 has a test programme destined to verify the electrical, cryogenic and quench performance of the magnets for machine operating conditions as well as providing a sampled field quality evaluation. From the magnet production and delivery points of views the test programme is used to monitor the overall magnet manufacturing quality. Given the environment and...Go to contribution page
-
Roberto Saban (CERN)19/01/2005, 16:05Effect of the compressed Schedule on the InstallationFollowing the uncertainty of the installation schedule, the HCWG focussed on the commissioning of two sectors around an even point in parallel augmented by a number of additional constraints. This exercise, which was published as a Management Report, yielded commissioning times and resource needs which can be scaled –within reasonable limits- to the requirements of the final...Go to contribution page
-
Mr Rüdiger Schmidt (CERN)19/01/2005, 16:40Effect of the compressed Schedule on the InstallationThe roadmap towards fully operational LHC controls will be discussed. Controls for beam operation are similar to other CERN accelerators. From the experience gained in the TI8 tests, with milestones such as the commissioning of LEIR, TI2, the controls for LHC will be realised with the same building blocks as used today. Hardware commissioning will provide a different challenge...Go to contribution page