Mr
S. Weisz
(CERN)
24/05/2005, 14:00
LHC Installation, comissioning and operation from CCC
Presentation+ Discussion
The LHC Installation planning was originally articulated with 4 main successive
phases: the installation of the general services, the installation of the cryogenic
line (QRL), the installation of the machine elements and the hardware commissioning.
While the installation of the general services is now almost finished - see
presentation by K. Foraz and S. Grillot -, several problems and...
Mr
M. Poehler
24/05/2005, 14:40
LHC Installation, comissioning and operation from CCC
Presentation
Dès fin 2001, la section Design Office TS-CE est mandatée pour l’étude et la
conception d’une nouvelle salle de contrôle des accélérateurs. Après de multiples
variantes d’études et d’implantation, la direction CERN retient en début 2004, sur la
base de facteurs économiques, le projet CCC, consistant en l’extension et le
réaménagement de la PCR existante. Un Working Group TS Infrastructure...
Mr
M. Batz
24/05/2005, 15:00
LHC Installation, comissioning and operation from CCC
Presentation
Control room operation of the Technical Infrastructure under the responsibility of
the Technical Support Department (TS) was carried out for decades based on the
round-the-clock operation from the Technical Control Room (TCR). The TCR functions
and services have been integrated in the AB Department in January 2005 and will
finally be assumed by the CERN Control Centre (CCC) in the...
Mr
J. Stowisek, Mr
S. Roy
24/05/2005, 15:20
LHC Installation, comissioning and operation from CCC
Presentation
In the summer of 2005, the Technical Infrastructure Monitoring (TIM) system will
replace the Technical Data Server (TDS) as the monitoring system of CERN’s technical
services. Whereas the TDS was designed for the LEP, TIM will have to cope with the
much more extensive monitoring needs of the LHC era. To cater for this, the new
system has been built on industry-standard hardware and...