24–26 May 2005
Archamps
Europe/Zurich timezone

Session

Session 4

not assigned
24 May 2005, 16:00
JURA building (Archamps)

JURA building

Archamps

Site d'Archamps F-74160 Archamps

Conveners

Session 4: LHC machine & Experiments

  • K. Potter (TS-HDO)

Presentation materials

There are no materials yet.

  1. Mr D. Lacarrere, Mr F. Butin, Mr J. Osborne, Mr S. Evrard
    24/05/2005, 16:00
    LHC and Experiments
    Presentation
    Following handover by the civil engineering contractors, the new LHC experimental areas are being fitted-out with appropriate infrastructure and technical services. In parallel, and in order to make up for the short time available, the installation of the detectors has already started in the experimental caverns. In addition, the LHC machine installation now has a non-negligible impact on...
    Go to contribution page
  2. Mr M. Gastal
    24/05/2005, 16:40
    LHC and Experiments
    Presentation
    The ALICE experimental area management team faces various challenges when it comes to sharing scarce resources, indispensable to any efficient installation in a category one worksite. Space, cranes, jigs, and personnel with key competences have to be carefully allocated to activities so as to avoid slowing down work progress. To this intent, a resource loaded planning has been developed...
    Go to contribution page
  3. Mr J.C. Gayde
    24/05/2005, 17:00
    LHC and Experiments
    Presentation
    La section TS/SU-EM fournit les informations géométriques de formes, dimensions et positions des infrastructures des cavernes et des détecteurs des expériences LHC. Elle intervient à toutes les étapes de construction et ses opérations sont dépendantes des autres chantiers, des entreprises en particulier, et de la configuration changeante des lieux. Les travaux de TS/SU-EM dans les...
    Go to contribution page
  4. Mr J. Ridewood
    24/05/2005, 17:20
    Presentation
    A summary of the general service requirements for a large warm dipole magnet and the challenges and issues associated with their installation will be presented. The LHCb spectrometer magnet will be used as an example, covering principally the power supply, cabling and cooling water system from conception to realisation and commissioning.
    Go to contribution page
  5. Dr D. Macina
    24/05/2005, 17:40
    LHC and Experiments
    Presentation
    The LHC experiments are building very complex detectors which will cope with the very high collision energy and luminosity provided by the LHC. The final commissioning of these detectors will require special beam conditions during the very early stage of the LHC operation. In addition, the five experiments will have a number of different requests in order to maximize the physics discovery...
    Go to contribution page
Building timetable...