    • 09:00 09:15
      Communications, approval of previous meeting minutes , meetings outside CERN 15m
      Speaker: Mazzucato, M
      Minutes
    • 09:15 09:45
      Report from the security workshop and proposal for long term Registration/VO management 30m
      Speaker: Kelsey, D
      transparencies
    • 09:45 10:15
      Presentation of the Implementation plan and status of the ramp up of the GOC operations Presentation of the document describing a set of service accounting parameters 30m
      Speaker: Gordon, J.
    • 10:15 10:45
      Ramp up of GUS and Call Center 30m
      Speaker: Kupsch, R.
      transparencies
    • 10:45 11:15
      Coffee break 30m
    • 11:15 11:45
      Term of reference and progress on the Grid interoperability Group 30m
      Speaker: White, Vicky
      transparencies
    • 11:45 12:15
      Progress in LCG tasks : Installation tool, Audit requirements 30m
      Speaker: Bird I.
      transparencies
    • 12:15 13:45
      Lunch break 1h 30m
    • 13:45 14:15
      Report on LHCC conclusions and POB discussion 30m
      Speaker: Robertson, Les
      transparencies
    • 14:15 14:45
      Discussion of the new LCG-2 schedule: Introduction, status and issues 30m
      Speaker: Bird I.
      transparencies
    • 14:45 16:15
      Detailed plans and schedules on production service operations 1h 30m
      The core group will start providing production service by Feb 9th The national GDB members representing Centers willing to be part of the core group will make a 10’ minutes presentation each: CERN, Italy, Spain, FZK, NIKHF, FNAL, Taipei, RAL….. (Centers willing to join the core group please confirm by mail)
      Speaker: National GDB members representing core group centres
    • 16:15 16:45
      Coffee break 30m
    • 16:45 17:25
      16.30 Updated detailed plans and schedule to start DC preparation on LCG-2 from February 9th 40m
      The discussion will include availability of software, using POOL and related RLS service, filling of the RLS catalog, appointment and plans of the experiment commissioning team
    • 17:25 17:55
      Final discussion and consensus plans 30m
    • 17:55 18:10
      AOB 15m