Details from the presentation can be taken from the minutes:
One additional point to fllow up is the future plan for the TPC gas system:
1) the tests in Bldg. 167 should be finished by the end of 2004.
2) beginning of next year the system can be installed on its final position at the ALICE pit.
3) further tests should be made with a test volume (80m3 available on the ALICE site). Afterwards
the gas system can be connected to the TPC fieldcage.
The exact pipe layouts for these tests need to be discussed.