SNS Linac System

10 Oct 2005, 12:00
30m
Bldg. 40, Room 40-S2-A01 (CERN)

Bldg. 40, Room 40-S2-A01

CERN

invited Opening Session

Speaker

Mark Champion (Oak Ridge National Laboratory / Spallation Neutron Source)

Description

The Spallation Neutron Source (SNS) project, which is scheduled for completion in Spring 2006, will utilize 100 RF systems for acceleration and bunching of the H- beam. Ninety-six of these systems drive the Linac, which was successfully commissioned with beam in Aug-Sep 2005. The remaining four RF systems are presently being tested in preparation for the Ring commissioning run, scheduled for Winter 2005-2006. In this paper the SNS RF systems will be described along with some operational results and plans for a power upgrade project, which will require an additional 38 RF stations.

Primary author

Mark Champion (Oak Ridge National Laboratory / Spallation Neutron Source)