Compatibility of Hardware Commissioning with Installation: Machine

13 May 2005, 09:15
15m
864-1-C02 (CERN, Prévessin)

864-1-C02

CERN, Prévessin

Speaker

Katy Foraz (TS-IC)

Description

The “proper” hardware commissioning will start once the machine and experimental elements in the tunnel are installed and the individual systems tests are done, in both sectors around an even point. This implies co-activities between the two phases; as for example individual systems tests (such as short circuit tests, etc.) will be done during the installation phase without disturbing its advancement; magnets will be transported through one sector during its hardware commissioning, etc.. The co-activities between installation (machine and experiments) and hardware commissioning, will be presented, as well as solutions adopted so far for an easy cohabitation.