GIF++ installation and schedule meeting
### July 15: 8.30-16
SAFETY INSPECTION AT 3PM!!!!
Impact need to be adjusted for 7/7 24/24. Please send to me impact number.
Each setup should nominate one/two person for patrol rights. Training today at about 6pm.
CSC, RPC, MDT,MM, DT
MM: try to add final chamber today in same position of small chambers. It might be needed to adjust the height of MM&MDT. Discussion after meeting on site.
MM will move out either Friday evening or Saturday. Need to open safety exit --> FREE ACCESS needed. Patrol after.
RPC will install air conditioning system.
Investigate possibility to fit ATL-RPC inside ATL-MDT frame
### July 22: 8.30-16 (concrete door need to be open)
ATL-RPC installation: detector and crate
Investigate possibility to fit ATL-RPC inside ATL-MDT frame
Combined test in August ATL-RPC & ATL-MDT 1 week
MDT move out beam, MM move in place of MM
### July 29: 8.30-16 (concrete door need to be open)
DT will install the extra-rails. Coordinate with CSC for installation.
third cable tray: RP approval needed
(Roberto will check who is in charge of the checks)
### August 5: 8.30-16
???
Plan wee main user:
Wed: --> 6pm SOURCE OFF up to 9 pm (assuming good beam is delivered continuously)
ABS factor scan will be discussed and agreed for upstream this afternoon (after MD period).
Thu: SOURCE OFF during the day from about 3 hours
Fri
Sat
Sun
Mon
Tue
Wed --> 8am