GIF++ installation and schedule meeting
### July 22: 8.30-16 (concrete door need to be open)
VF is coming to repair the irradiator
Ongoing work on the light
ATL-RPC installation: detector and crate
Investigate possibility to fit ATL-RPC inside ATL-MDT frame
Combined test in August ATL-RPC & ATL-MDT 1 week (to be discussed with Giulio today)
CMS-RPC remove one trolley (put back in August)
MDT move out beam, MM move in front of the source on Monday.
MDT request to be back on beam 1st week of beam period in August (to be discussed)
### July 29: 8.30-16 (concrete door need to be open)
DT will install the cables. Coordinate with CSC for installation.
third cable tray: RP approval needed
(Roberto will check who is in charge of the checks)
### August 5: 8.30-16
DT will install the extra-rails. Coordinate with CSC for installation.
Plan week parassitic user after PANDA:
Wed: Gaetan, Yan and all: check beam and report.
Thu:
Fri
Sat
Sun
Mon
Tue
Wed