### August 12-13: 8.30-17
Close bunker concrete door: Thursday 13 2pm
Restart radiation Thursday 13 6pm
Opening of the roof: first time, no experience. Protect detector from dust.
installation DT chamber
CMS-RPC 0 trolley in preparation area
ATL-MDT frame on beam line without telescope
ATL-MM install cables (false floor need to be opened)
ATL-RPC install cables (false floor need to be opened)
### August 19: 8.30-16
Open bunker concrete door
CMS-DT complete install cables (false floor need to be opened)
CMS-RPC 0 trolley in bunker (upstream)