GIF++ installation and schedule meeting
False floor should be closed immediately after work completed.
Pipe to exhaust outside heat from CMS-RPC air condition units (budget from RPC)
### August 19: 8.30-16
Open bunker concrete door
CMS-RPC 0 trolley in bunker (upstream)
ATL-MDT install telescope
ATL-MM move out of beam line
### August 26: Time to be decided according to SPS schedule/news
bunker will remain closed. Free access if needed.
Move out ATL-MDT
Move on beam ATL-MM
Move CMS-GRPC closer to source
Move CMS-CSCback out of beam (CMS-CSCfront will stay on beam line)
Move CMS-DT on beam line
CMS-CSC copper pipe need to be replaced by something else (Fred, Roberto).
During beam time: 9.30am meeting in GIF control room
1st week
Beam intensity max 10 k mu/spill
2nd week
Try beam at 50 k mu/spill (request from ATL-MM)
Wed:
Thu:
Fri
Sat
Sun
Mon
Tue
Wed