Description
Chairman: José Miguel Jiménez
Scientific Secretary: J.Ph. Tock
The baseline LIU installation activities corresponding to both ion and proton upgrades will be reviewed to show-up changes approved and/or proposed with respect the 2014 baseline. An advanced draft schedule of LIU activities will be presented, underlining the corresponding support needed from the various CERN groups together with the required technical expertise.
The baseline HL-LHC installation activities will be reviewed to show-up changes approved and/or proposed with respect the 2014 baseline. A draft schedule of HL-LHC activities will be presented, underlining the impact of civil engineering and of other preparatory works. on the infrastructure accessibility and reviewing options of coactivity.
The LHC experiments have planned significant maintenance and upgrade efforts for LS2. ALICE and LHCb will implement major upgrades with important changes to the entire apparatus, while ATLAS and CMS will perform their major detector upgrades only during LS3. The presentation will review the LS2 plans of the experiments and will focus on support needed during (E)YETS from...
The non-LHC experiments have planned significant maintenance and consolidation efforts. The presentation will review the most relevant activities and will focus on support needed during (E)YETS from the technical sector.
After a brief review of the Plan Tool implementation, the first feedback will be evaluated and the consistency with LIU will be reviewed as a pilot check.
Following the first feedback from Plan Tool, a preliminary version of the master schedule will be presented, highlighting the process of validation of interfaces between activities and groups. The impact of all activities restricting accesses (civil engineering, cabling campaigns, access and alarms system renovations, etc.) will be reviewed.