-
Julie Coupard, Katy Foraz04/02/2009, 08:30The first shutdown of the LHC machine started on the 17th of November 2008. In addition to typical shut-down interventions and the works already foreseen (e.g. phase 1 collimator installation), some additional consolidation work is needed. On top of this comes the work caused by the 19 September incident and the subsequent tests carried out in November and December. This talk will give an...Go to contribution page
-
Julie Coupard, Katy Foraz04/02/2009, 09:05Alternative options for the current shutdown will be presented. These options include warming up additional sectors to complete the consolidation activities. The potential impact of these revised schedules on the beam schedule in 2009, as well as the length and timing of the following shutdown will also be presented.Go to contribution page
-
Mario Batz04/02/2009, 09:25As a complement to the previous talk, a number of questions, that will need to be addressed in order to consider LHC beam operation over the winter 2009-10, will be raised.Go to contribution page
-
Rüdiger Schmidt04/02/2009, 09:40Layout and electrical circuits of the LHC machine are well documented in the databases and the data has been used throughout hardware and beam commissioning. During the shutdown a number of changes will be made all around the accelerator, to different systems. The presentation will address in what areas changes are expected and how the changes are (or are not) documented. Proposals will be...Go to contribution page
-
Pierre Strubin04/02/2009, 10:40There may be circumstances when a sector has to be partially or totally warmed-up to temperatures above 80 K, that is when thermal dilatation starts to play a role. Some equipment have been identify as presenting a risk, like the non-conform "plug-in" modules in the arcs. Because of motion induced by thermal dilatation, the electrical (ElQA) quality control may also have to be done again...Go to contribution page
-
Roberto Saban04/02/2009, 11:10Following the completion of the installation last year, several reviews (ATC, LTC, MARIC) were carried-out to draw up the inventory of the spare LHC components. A detailed summary of these exercises will be given and the present situation with the spares following the September 19th incident will be presented.Go to contribution page
Choose timezone
Your profile timezone: