BI/TB on LIU-SPS specfications, BLM detector checks, OAF, LHC status and FCC
866 2-D05
CERN
1) LIU-SPS specifications:
A) Missing action points for BSRT and BGI
B) Separate document for ion requirements.
2) Injector BLM detector checks:
A) Question whether simple homodyne principle would not solve the problem
3) OAF:
A) Coming presentations will cover status and plans for framework and instruments reports
4) LHC status:
Issues pending resolution:
A) BPM firmware for post-mortem (being tested today)
B) BWS acquisition with intensity limits as function of beam energy
C) BCT DC acquisition blocked during 24 hours - what about the SMP link?
Safe beam expected by tomorrow (Friday
5) FCC:
- Meetings will be launched by Hermann during 2016 to
A) identify where R&D efforts are required (with milestones)
B) Come up with a draft cost estimate based on today's figures