GIF++ installation and schedule meeting
Maintenance of the irradiator:
March 14-16
Maintenance of the RAMSES:
March 18 (to check if it can be done together with maintenance of the irradiator)
-HVAC
installation scheduled for March 21 to April 1.
onsite meeting with EN to understand space needed for installation: tomorrow March 3. Recommended participation of CMS-RPC (and CMS-DT).
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.
Thursday March 3:
- bunker will remain closed
Friday March 4:
CSC scan (during morning)
March 10:
-???
-beam trigger scintillators:
Nicolas and Yuri replaced the downstream with one belonging to them.
Old one (GIF) needed urgently to proceed with repairing
Wednesday march 3: (exceptional) opening 1 hour for installation of HV connectors
-GIF exhaust will be upgraded soon (about 2 weeks)