GIF++ installation and schedule meeting
Maintenance of the irradiator:
March 14-16
ATL-MM, CMS-GEM, ATL-RPC, CMS-CSC, ATL-TGC, CMS-RPC should be on site (bunker) Thursday March 10 8.30 am to move or to understand what is needed to allow the maintenance of the irradiator.
Table with actions required will be distributed tomorrow morning.
Maintenance of the RAMSES:
March 18 (to check if it can be done together with maintenance of the irradiator)
-HVAC
installation scheduled for March 21 to April 1.
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.
---
Thursday March 10:
- bunker will remain closed
Friday March 11:
CSC: scan (late morning + afternoon)
RPC: scan (late morning + afternoon)
BLM: test chambers Friday March 11 morning.
March 17:
-???
-beam trigger scintillators:
Nicolas and Yuri replaced the downstream with one belonging to them.
Old one (GIF) needed urgently to proceed with repairing
One additional signal+HV for second scintillators upstream (scintillator is from CMS-RPC)
-GIF exhaust will be upgraded soon (about 1 weeks, to be confirmed by Frederic)