Cryogenic piping

27 Apr 2016, 13:30
3179 (CERN)

3179

CERN

Ideas2

Description

• Cryogenic piping will be installed before the TPC. This will be installed in parallel with the installation of the TPC support structure.
• Upper manifolds will be installed and support from the cryostat and feed thrus.
• Floor manifolds will be installed in two parts. The vertical members will be installed from outside down through their ports. The lower manifolds will be attached and welded from the floor.
• Piping supports to the north wall.
• Piping supports to the floor.