26–29 Apr 2016
CERN
Europe/Zurich timezone

Session

Field cage top and bottom

29 Apr 2016, 08:30
3179 (CERN)

3179

CERN

Ideas2

Description

• Packaging estimate.
• Handling equipment.
• Temporary structure and removal.
• Subassembly required with ground planes.
• Mounting onto CPA.
• Access needed and plans.
• Top is 3.6 m full assembly and bottom is 2.5 reduced assembly to mount on vertical CPA panel.
• Deploy panels inside cryostat. Top panel – lifting hardware, latching devices, electrical, removal of hardware. Bottom panel – lowering hardware, addition of 1.1 m section, electrical, access platform on top of panel, removal of hardware.
• Electrical connections.
• Any test of electrical connections after installation inside the cryostat?

Presentation materials

There are no materials yet.

Building timetable...