-Beam:
- Info from Adrian:
NA63 will run positrons throughout their period. Like this there will be no muons.
XTDV installation: no news. Potential problem for irradiation during CMS-ECAL beam time June 9- June 29; July 27 - Aug 10; Sept 21 - Sept 28.
- Discussion for HVAC commissioning:
probably after coming test beam. i.e. starting from June 9th
-more tables and chairs in control room.
Prepare plan of CR (Giuseppe)
---
-Wednesday (May 18th)
-Thursday (May 19th):
no source scan. Stable irradiation.
Intervention on users DCS PCs:
pcgifdcs01
pcgifdcs02 (main USER DCS computer of GIF DCS)
pcgifdcs03
pcgifdcs04 (main DCS computer for CMS RPC)
pcgifdcs05 (main DCS computer for ATLAS RPC)
-Next Tuesday (May 24th)
CMS-DT source scan (downstream) for small tube
CMS-CSC possible scan after.
-Next Wednesday (May 25th)
complete installation before test beam.
Concrete blocks need to be open.
-Next Thursday (May26th):
test beam.
-----
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.