GIF++ installation and schedule meeting
-Beam:
- Info from Adrian:
XTDV installation:
it will require 3 days with source off. For the moment it is scheduled for June 9.
Without installation: potential problem for irradiation during CMS-ECAL beam time June 9- June 29; July 27 - Aug 10; Sept 21 - Sept 28.
- Discussion for HVAC commissioning:
probably after coming test beam. i.e. starting from June 9th
-more tables and chairs in control room.
Prepare plan of CR (Giuseppe)
---
-Tuesday (May 24th)
CMS-DT source scan (downstream) for small tube
CMS-CSC possible scan after.
-Next Wednesday (May 25th)
complete installation before test beam.
Concrete blocks need to be open.
CMS-CSC connected to GIF water cooling
-Next Thursday (May26th):
test beam.
-----
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.