•Organisation of hardware commissioning, meetings, …
•What happens before powering tests after cooldown
•Commissioning of Warm sectors, Cold sectors and sector 34: what needs to be done? What can be dropped?
•When should we work: 2 shifts during 5 days versus 3 shifts during 7 days, MPP analysis, what can be done in a nightshift – WE? Bottlenecks in manpower
•Rules for patrols during powering tests