GIF++ installation and schedule meeting
Technical help/interventions
-All technical interventions/requests will take place on Thursday. Giuseppe will be available to follow the requests from the users.
-False floor unstable in front of gas supply panel S01 --> Giuseppe to check
-Beam:
-XTDV installation:
planned for July 20 - July 22 (no more news. No reply from EN/Adrian)
After SPS meeting:
-
XTDV installation. Planning is here: https://indico.cern.ch/event/549613/contributions/2228943/subcontributions/200550/attachments/1309592/1958922/GIF_XTDV_installation_EATM.pdf Only the downstream one will be installed. However, the new tables did not leave Portugal yet. This should happen tomorrow. It is possible 1 or 2 days delay w.r.t. the schedule in the presentation;
- Discussion for HVAC operation:
New settings:
20 C 45% RH
reached 21.5 56%
Humidity setting not achieved (min is 50%)
Humidity is not removed as expected. Discuss with EN-CV-Aziz, Jerome.
Other works planned at EHN1 and affecting GIF operation:
-
A heavy magnet MNP22 (60T) needs to be moved inside EHN1. Several options are being considered but, for this activity it is possible that some concrete shielding blocks and some other structures in EHN1 have to be temporary removed/displaced. This can include the temporary removal during one day of part of the exhaust gas line of GIF++. This activity will happen probably in September;
-
The overhead crane rails in EHN1 should be renovated. Details are here: https://indico.cern.ch/event/549613/contributions/2240144/attachments/1309284/1958341/EHN1_rails.pdf This activity will imply one week of inactivity for the cranes in EHN1 in the area where GIF++ is located. This activity is being scheduled at the end of the beam time in the weeks 49-51 (December 2016).
Wednesday 20
CMS-CSC, ATL-TGC, EP-DT, ATL-MM
Thursday 21
source off - XTDV installation
Friday 22
restart asap
ATL-sTGC mod0 (2 hours). After test sTGCmod0 will be moved on the side of the source.
Wednesday July 27th
smallTGC will be moved in front of the source.
(ATL-NSW-MM cable installation. False floor need to be open. Not urgent (needed by beginning-September)
Giuseppe to contact Zhen (ATL-NSW-MM) to inform bunker will be open.
Thursday July 28th
???
*ATL-NSW-MM gas supply connection: is it done?
*ATL-CSC test (assign position, gas panel, ...)
-----
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.