GIF++ installation and schedule meeting
Technical help/interventions
-All technical interventions/requests will take place on Thursday. Giuseppe will be available to follow the requests from the users.
-Beam:
-XTDV installation:
News after downstream XTDV installation from EN/Adrian:
From now on, a small change is introduced to the operation of the irradiator until further notice:
-
Also zone PPE144 needs to be closed (not only PPE154).
This is because we will not re-establish the upstream shielding block, until the upstream XTDV is also available.
Please note, that for entering GIF you will (have to) stop the electron beam to CMS-ECAL (as it always was). So for PPE154 access, see directly with CMS control hut.
- Discussion for HVAC operation:
New settings:
20.5 C 45% RH
reached 21.5 56%
Humidity setting not achieved (min is 50%)
Humidity is not removed as expected. Giuseppe discuss with EN-CV-Aziz, Jerome (arrange a meeting).
Other works planned at EHN1 and affecting GIF operation:
-
A heavy magnet MNP22 (60T) needs to be moved inside EHN1. Several options are being considered but, for this activity it is possible that some concrete shielding blocks and some other structures in EHN1 have to be temporary removed/displaced. This can include the temporary removal during one day of part of the exhaust gas line of GIF++. This activity will happen probably in September;
-
The overhead crane rails in EHN1 should be renovated. Details are here: https://indico.cern.ch/event/549613/contributions/2240144/attachments/1309284/1958341/EHN1_rails.pdf This activity will imply one week of inactivity for the cranes in EHN1 in the area where GIF++ is located. This activity is being scheduled at the end of the beam time in the week 50 (December 2016).
Wednesday 27
detector moved to free space for beam pipe
ATL-sTGC-QS1 removed
ATL-sTGC-small moved in front of the source
Thursday 28
ATL-MM source scan (pm) - upstream only
Friday 29
short access requested by CMS-CSC
Wednesday August 3rd
ATL-sTGC-QL1 will be installed in the bunker. Need to open the false floor.
upstream absorption set to 4.6 from July 28 until next Wednesday August 3rd (ATL-MM and CMS-RPC agreed).
(ATL-NSW-MM cable installation. False floor need to be open. Not urgent (needed by beginning-September)
Giuseppe to contact Zhen (ATL-NSW-MM) to inform bunker will be open: Zhen is on holiday (work will be done after test beam).
Thursday August 4th
???
*ATL-CSC test (assign position, gas panel, ...):
Agree with Giuseppe on the routing of pipes and cables.
Position is in place of ATL-MM
Installation after August test beam
-----
-AIDA2020 funds for work at GIF:
NIcolas Zagadinis, Paolo Iengo, ATL-RPC, ... will provide possible candidates for the application.