wed 17/8
ATL-TGC QL1 need bunker open. removal of chamber.
Temperature of nC5H12 buffer on DIP.
EP-DT false floor 1 tile (to be confirmed)
CMS-CSC vs ATL-RPC
CMS-CSC will move out for a couple of days not to be in front of RPC (to be re-discussed)
Downstream area setups: discussion about position and size (9 am)
Thu 18/8
plan according to test beam.