All heavy components entering into the PSB injection and extraction zones are lowered from a main shaft into the building 361 from surface to basement and then risen back to the PSB machine level via 2 shafts, by using 2 x 10t cranes.
The LIU extraction magnets are bigger than the existing ones and cannot be dismounted in parts compatible with the existing shaft dimensions. It is therefore proposed to increase one of the shaft¿s dimension to cope with this.