GIF++ installation and schedule meeting

→ Europe/Zurich
864/1-C02 - indisponible a partir du 24/04/2017 (CERN)

864/1-C02 - indisponible a partir du 24/04/2017

CERN

50
Show room on map
Roberto Guida (CERN)
    • 09:00 → 09:30
      Summary/feedback from last test beams in view of presentation at SMS meeting 30m

      All 2016 test beams. I put here also the old presentations we already discussed last Thursday.

      Speakers: Barbara Alvarez Gonzalez (CERN), Giulio Aielli (Universita e INFN Roma Tor Vergata (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno), Katerina Kuznetsova (Petersburg Nuclear Physics Institut (RU)), Korbinian Ralf Schmidt-Sommerfeld (Max-Planck-Institut fur Physik (DE)), Nicolas Zaganidis (Ghent University (BE)), Salvador Carrillo Moreno (Universidad Iberoamericana (MX))

      1-2 slides per setups which used beam

       

      slides from setups which did not use beam are welcome

       

       

       

    • 09:30 → 09:50
      Plan for next wednesday (MD) / thursday (source scan) 20m

      Thursday 13th

      no scan

      CMS-DT completed their test. Source can be set to 1.

      Short access needed to move CMS-DT out radiation cone.

       

      Wed Oct 19th

      open bunker: CMS.CSC but can be postponed

       

       

    • 09:50 → 10:10
      Report about tentative program for the “half-filter” test 20m
      Speakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)

      Proposal-1

      Install October 19

      Test October 20-21

      Move out October 21

       

      Proposal-2

      Enter on October 19

      Install October 24

      Test October 24-25

      Move out October 26

       

      ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.

      CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).

      CMS-DT (Ignacio) supporting the test. small preference for  Proposal-1.

      CMS-GEM (Ilaria) not in the bunker

      ATL-MDT (Bini) not in the bunker

      CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.

      ATL-MM (Barbara) not in the bunker

      EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.

      ATL-RPC (Giulio) not present

       

      Conclusion:

      Test will be performed next GIF week-time (wed Oct 19-26).

      We wait CSC and RPC to decide between Proposal-1 and Proposal-2

      Half-Filter will be removed right after test will be completed (Max 2 days). 

      Safety inspection for Wed Oct 19.

       

    • 10:10 → 10:40
      Iteration of new requests for tests at GIF 30m

      introduction, goal of the test, plan, needs

      Proposals discussed.

      Everybody confirmed to not see any problem with both installations as long as they were presented and do not interfere with current R&D test at GIF

      • LHCb-Sci 10m
        Speakers: Antonio Pellegrino (NIKHEF (NL), University of Groningen (NL)), Antonio Pellegrino (NIKHEF)
      • AIDA2020-Pellicole radiocromiche 10m
        Speaker: Francesco Fienga (Universita e INFN, Napoli (IT))
    • 10:40 → 10:50
      Plan for 2017 10m

      please provide info about:
      -new requests
      -plan for setups currently under test