    • 09:00 → 09:20
      Summary/feedback from last test beam (final look before presentation at SPS meeting) 20m

      All 2016 test beams. I put here also the old presentations we already discussed last Thursday.

      Speakers: Barbara Alvarez Gonzalez (CERN), Giulio Aielli (Universita e INFN Roma Tor Vergata (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno), Katerina Kuznetsova (Petersburg Nuclear Physics Institut (RU)), Korbinian Ralf Schmidt-Sommerfeld (Max-Planck-Institut fur Physik (DE)), Nicolas Zaganidis (Ghent University (BE)), Salvador Carrillo Moreno (Universidad Iberoamericana (MX))

      1-2 slides per setups which used beam

       

      slides from setups which did not use beam are welcome

       

       

       

    • 09:20 → 09:30
      Plan for next wednesday (MD) / thursday (source scan) 10m

      Thursday 20th

      half-filter profile - data taking ongoing

      scan  with half-filter

       

      Friday 21th

      Remove half-filter (2pm) Giuseppe will agree with transport team

       

      Wed Oct 26th

      open bunker:

      Remove half-filter and lifting tool

      False floor for ATL-nSW-MM (Zen) high voltage cables

      Visit for Wifi installation (Giuseppe)

       

       

    • 09:30 → 10:00
      Plan for 2017: Summary of requests received 30m

      New requests and plans of the current users should be finalized by tomorrow.

    • 10:00 → 10:20
      Report about the “half-filter” test 20m
      Speakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)

      Update October 20:

      Installation went smooth

      Safety visit ok

      Characterization/data taking on-going

       

       

      Proposal-1

      Install October 19

      Test October 20-21

      Move out October 21

       

      Proposal-2

      Enter on October 19

      Install October 24

      Test October 24-25

      Move out October 26

       

      ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.

      CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).

      CMS-DT (Ignacio) supporting the test. small preference for  Proposal-1.

      CMS-GEM (Ilaria) not in the bunker

      ATL-MDT (Bini) not in the bunker

      CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.

      ATL-MM (Barbara) not in the bunker

      EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.

      ATL-RPC (Giulio) not present

       

      Conclusion:

      Test will be performed next GIF week-time (wed Oct 19-26).

      We wait CSC and RPC to decide between Proposal-1 and Proposal-2

      Half-Filter will be removed right after test will be completed (Max 2 days). 

      Safety inspection for Wed Oct 19.

       

    • 10:20 → 10:30
      Iteration of new requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      Proposals discussed.

      Everybody confirmed to not see any problem with both installations as long as they were presented and do not interfere with current R&D test at GIF

      • LHCb-Sci 5m
        Speakers: Antonio Pellegrino (NIKHEF), Antonio Pellegrino (NIKHEF (NL), University of Groningen (NL))
      • AIDA2020-Pellicole radiocromiche 5m
        Speaker: Francesco Fienga (Universita e INFN, Napoli (IT))
      • Irradiation of scintillators for the CMS HCAL Upgrade 10m
        Speaker: Francesca Ricci-Tam (University of Maryland (US))
    • 10:30 → 10:40
      Announcement 10m