GIF++ installation and schedule meeting
-
-
09:00
→
09:20
Summary/feedback from last test beam (final look before presentation at SPS meeting) 20m
All 2016 test beams. I put here also the old presentations we already discussed last Thursday.
Speakers: Barbara Alvarez Gonzalez (CERN), Giulio Aielli (Universita e INFN Roma Tor Vergata (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno), Katerina Kuznetsova (Petersburg Nuclear Physics Institut (RU)), Korbinian Ralf Schmidt-Sommerfeld (Max-Planck-Institut fur Physik (DE)), Nicolas Zaganidis (Ghent University (BE)), Salvador Carrillo Moreno (Universidad Iberoamericana (MX)) -
09:20
→
09:30
Plan for next wednesday (MD) / thursday (source scan) 10m
Thursday 20th
half-filter profile - data taking ongoing
scan with half-filter
Friday 21th
Remove half-filter (2pm) Giuseppe will agree with transport team
Wed Oct 26th
open bunker:
Remove half-filter and lifting tool
False floor for ATL-nSW-MM (Zen) high voltage cables
Visit for Wifi installation (Giuseppe)
-
09:30
→
10:00
Plan for 2017: Summary of requests received 30m
New requests and plans of the current users should be finalized by tomorrow.
-
10:00
→
10:20
Report about the “half-filter” test 20mSpeakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)
Update October 20:
Installation went smooth
Safety visit ok
Characterization/data taking on-going
Proposal-1
Install October 19
Test October 20-21
Move out October 21
Proposal-2
Enter on October 19
Install October 24
Test October 24-25
Move out October 26
ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.
CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).
CMS-DT (Ignacio) supporting the test. small preference for Proposal-1.
CMS-GEM (Ilaria) not in the bunker
ATL-MDT (Bini) not in the bunker
CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.
ATL-MM (Barbara) not in the bunker
EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.
ATL-RPC (Giulio) not present
Conclusion:
Test will be performed next GIF week-time (wed Oct 19-26).
We wait CSC and RPC to decide between Proposal-1 and Proposal-2
Half-Filter will be removed right after test will be completed (Max 2 days).
Safety inspection for Wed Oct 19.
-
10:20
→
10:30
Iteration of new requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
LHCb-Sci 5mSpeakers: Antonio Pellegrino (NIKHEF), Antonio Pellegrino (NIKHEF (NL), University of Groningen (NL))
-
AIDA2020-Pellicole radiocromiche 5mSpeaker: Francesco Fienga (Universita e INFN, Napoli (IT))
-
Irradiation of scintillators for the CMS HCAL Upgrade 10mSpeaker: Francesca Ricci-Tam (University of Maryland (US))
-
-
10:30
→
10:40
Announcement 10m
-