GIF++ installation and schedule meeting
-
-
09:00
→
09:10
Plan for next wednesday (MD) / thursday (source scan) 10m
Thursday 27th
scan: CMS-CSC - pm
install LHCb-fibre sample
Friday 28th
ATL-CSC:
need access to install bubbler (15 min)
short access during next 4-5 days (15 min each)
Fine with all setup representatives. In case of problems (access too long or too frequent) please "rise a flag" immediatly.
Wed Nov 2nd
bunker closed
Install CMS-HCAL
-
09:10
→
09:45
Plan for 2017: Summary of requests received 35m
In attachment excel table with details of each request and first preliminary proposals discussed during meeting.
Test contact persons will be contacted soon to have short description to motivate the request for R&D activityPresent: CMS-CSC (Victor, Katerina), CMS-DT (Ignacio), ATL-MM_prototype (Barbara), ATL-MM_mod0 (Yan), EP-DT (Beatrice), CMS-GEM (Ilaria), ATL-MDT (Bini), ATL-TGC (Henso), CMS-RPC (Nicolas)
- 3 or 4 periods
CMS-CSC no able to reply. Depends on CMS-DT. It will write preference in 1 week time.
CMS-DT preference for 3
ATL-MM_prototype preference for 3
ATL-MM_mod0 preference for 3
EP-DT preference for 3
CMS-GEM preference for 3
ATL-MDT preference for 3 (if possible with 3 weeks also in the middle)
ATL-TGC preference for 3
CMS-RPC preference for 3
- proposal 1 bis:
CMS-CSC in case of 3 beam periods it is "perfect"
CMS-DT ok
ATL-MM_prototype ok
ATL-MM_mod0 ok
EP-DT ok
CMS-GEM ok
ATL-MDT ok (request to have middle period a bit later-1 or 2 weeks later - Option 1ter)
ATL-TGC ok
CMS-RPC ok
- proposal 1 ter: please think about for next week.
-
09:45
→
10:15
Report about the “half-filter” test 30m
Discussion postponed to next week (November 3rd)
Speakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)Update October 20:
Installation went smooth
Safety visit ok
Characterization/data taking on-going
Proposal-1
Install October 19
Test October 20-21
Move out October 21
Proposal-2
Enter on October 19
Install October 24
Test October 24-25
Move out October 26
ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.
CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).
CMS-DT (Ignacio) supporting the test. small preference for Proposal-1.
CMS-GEM (Ilaria) not in the bunker
ATL-MDT (Bini) not in the bunker
CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.
ATL-MM (Barbara) not in the bunker
EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.
ATL-RPC (Giulio) not present
Conclusion:
Test will be performed next GIF week-time (wed Oct 19-26).
We wait CSC and RPC to decide between Proposal-1 and Proposal-2
Half-Filter will be removed right after test will be completed (Max 2 days).
Safety inspection for Wed Oct 19.
-
10:15
→
10:30
Iteration of new requests for tests at GIF 15m
introduction, goal of the test, plan, needs
-
10:30
→
10:40
Announcement 10m
1) Maintenance of the irradiator: end of March - 3 days. Nobody see problems/conflicts
2) Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator
3) Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted)
4) INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm)
-
09:00
→
09:10