GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Roberto Guida (CERN)
    • 09:00 → 09:10
      Plan for next wednesday (MD) / thursday (source scan) 10m

      Thursday 4th

      scan: CMS-CSC - pm

       

       

      Wed Nov 9th

      bunker closed

       

       

    • 09:10 → 09:45
      Plan for 2017: Summary of requests received 35m

      Short description to motivate the request for R&D activity needed by the end of current week (November 4th)

      Present: CMS-CSC (Katerina), CMS-DT (Ignacio), ATL-MM_prototype (Barbara), ATL-MM_mod0 (Yan), EP-DT (Roberto), CMS-GEM (Ilaria), ATL-TGC (Henso), CMS-RPC (Nicolas)

       

      CMS-CSC (Katerina) opt3rd

      CMS-DT (Ignacio) no preference

      ATL-MM_prototype (Barbara) opt3rd

      ATL-MM_mod0 (Yan) opt4th

      EP-DT (Roberto) no preference

      CMS-GEM (Ilaria) no preference

      ATL-TGC (Henso) opt4th

      CMS-RPC (Nicolas) opt4th

       

      Option 4th will be submitted to SPS coordinator

       

    • 09:45 → 10:15
      Report about the “half-filter” test 30m

      postponed wed Nov10

      Speakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)

      Update October 20:

      Installation went smooth

      Safety visit ok

      Characterization/data taking on-going

       

       

      Proposal-1

      Install October 19

      Test October 20-21

      Move out October 21

       

      Proposal-2

      Enter on October 19

      Install October 24

      Test October 24-25

      Move out October 26

       

      ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.

      CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).

      CMS-DT (Ignacio) supporting the test. small preference for  Proposal-1.

      CMS-GEM (Ilaria) not in the bunker

      ATL-MDT (Bini) not in the bunker

      CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.

      ATL-MM (Barbara) not in the bunker

      EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.

      ATL-RPC (Giulio) not present

       

      Conclusion:

      Test will be performed next GIF week-time (wed Oct 19-26).

      We wait CSC and RPC to decide between Proposal-1 and Proposal-2

      Half-Filter will be removed right after test will be completed (Max 2 days). 

      Safety inspection for Wed Oct 19.

       

    • 10:15 → 10:30
      Iteration of new requests for tests at GIF 15m

      introduction, goal of the test, plan, needs

      Proposals discussed.

      Everybody confirmed to not see any problem with both installations as long as they were presented and do not interfere with current R&D test at GIF

      • ATL-CSC 5m
        Speaker: Cenk Yildiz (University of California Irvine (US))

        Hi Roberto,

        We are planning some more tests with the Atlas CSC chamber in 2017.

        We will be repairing two chambers and want to test them before reinstallation in February or March. Each chamber needs only one or two days close to the source. Will there be time available for this test?
         

        Regards,

        Michael Schernau

         

         

        requested position: on the side of the Glass-RPC rack. To be discussed (after April RPC will probably replace the present rack with larger one).

         

      • AIDA2020-Pellicole radiocromiche 5m
        Speaker: Francesco Fienga (Universita e INFN, Napoli (IT))

        On-site check next week.

      • Irradiation of scintillators for the CMS HCAL Upgrade 10m
        Speaker: Francesca Ricci-Tam (University of Maryland (US))

        Installed: Wednesday November 2nd

    • 10:30 → 10:40
      Announcement 10m

      1) Maintenance of the irradiator: end of March - 3 days. Nobody see problems/conflicts

      2) Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator

      3) Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted)

      4) INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm)