GIF++ installation and schedule meeting
-
-
09:00
→
09:10
Plan for next wednesday (MD) / thursday (source scan) 10m
-
09:10
→
09:25
Plan for 2017 15m
Short description to motivate the request for R&D activity
CMS-DT plan for 2017.
4 months (assuming safety factor 3 for HL-LHC and 100% duty cycle of irradiator) of irradiation at absorption factor 15.
4 options presented by Ignacio:
1) This winter (about November 2016 to April 2017)
2) During the June-July 2017 period(compromise ½ of safety factor)
3) August-September 2017 periods (compromise ½ of safety factor)
4) Next winter (about November 2017 to April 2018)
CMS-muon community and CMS-DT prefer option 4.
Preliminary comments:
ATL-MM (Barbara): upstream, so not affected
ATL-sTGC (Henso, Yan): not compatible with TGC request, but it might be that TGC ageing test will be completed. It will remain the mass-production test which requires 0.5 day/week (typical time for the source to be at max irradiation will be 0.5 hour/week).
CMS-CSC (Katerina, Victor): ok for CSC
EP-DT (Beatrice): no preference. ok
CMS-GEM (Ilaria): fine with option 4
CMS-RPC (Nicolas, Andrea): fine with option 4.
ATL-RPC: not present
ALT-NSW-MM (Zhen): no preference, but not clear plan for the moment. MM plan is very similar to sTGC.
-
09:25
→
09:55
Report about the “half-filter” test 30m
postponed wed Nov10
Speakers: Domenico Dattola (Universita e INFN Torino (IT)), Ignacio Redondo Fernandez (Centro de Investigaciones Energéti cas Medioambientales y Tecno)Update October 20:
Installation went smooth
Safety visit ok
Characterization/data taking on-going
Proposal-1
Install October 19
Test October 20-21
Move out October 21
Proposal-2
Enter on October 19
Install October 24
Test October 24-25
Move out October 26
ATL-TGC (Isabel) not aware of any reason to stop. No preferred proposal.
CMS-CSC (Katerina) not aware of any reason to stop. No preferred proposal (tbc by tomorrow).
CMS-DT (Ignacio) supporting the test. small preference for Proposal-1.
CMS-GEM (Ilaria) not in the bunker
ATL-MDT (Bini) not in the bunker
CMS-RPC (Ian) not aware of any reason to stop. No preferred proposal.
ATL-MM (Barbara) not in the bunker
EP-DT (Antonio) not aware of any reason to stop. No preferred proposal.
ATL-RPC (Giulio) not present
Conclusion:
Test will be performed next GIF week-time (wed Oct 19-26).
We wait CSC and RPC to decide between Proposal-1 and Proposal-2
Half-Filter will be removed right after test will be completed (Max 2 days).
Safety inspection for Wed Oct 19.
-
09:55
→
10:10
Iteration of new requests for tests at GIF 15m
introduction, goal of the test, plan, needs
-
ATL-CSC 5mSpeaker: Cenk Yildiz (University of California Irvine (US))
CSC are installed on the side of CMS-GlassRPC ("U2")
Connected to gas and HV.
In the bunker until March/April 2017
Hi Roberto,
We are planning some more tests with the Atlas CSC chamber in 2017.
We will be repairing two chambers and want to test them before reinstallation in February or March. Each chamber needs only one or two days close to the source. Will there be time available for this test?
Regards,
Michael Schernau
requested position: on the side of the Glass-RPC rack. To be discussed (after April RPC will probably replace the present rack with larger one).
-
Irradiation of optical fiber Belle II - PID 5m
installation scheduled for November 17 or 24
Speaker: Ezio Torassa (Universita e INFN, Padova (IT))
-
-
10:10
→
10:20
Material door: EN proposal 10m
-
10:20
→
10:30
Announcement 10m
1) Maintenance of the irradiator: end of March - 3 days. Nobody see problems/conflicts
2) Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator
3) Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted)
4) INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm)
-