GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Martin Richard Jaekel (CERN), Roberto Guida (CERN)
    • 09:00 → 09:10
      Plan for next wednesday (MD) / thursday (source scan) 10m

      Thursday 17th

      scan: EP-DT-am

      CMS-CSC - pm, ATL-MM -3-7pm

      CMS-DT: Jacopo might need very short access. Need to be agreed with other users doing source scan.

      Measurement of gamma flux downstream; Gerardo am-pm togheter with other users

       

       

      Wed Nov 23

      bunker closed

       

       

    • 09:15 → 09:30
      Iteration of new requests for tests at GIF 15m

      introduction, goal of the test, plan, needs

      Proposals discussed.

      Everybody confirmed to not see any problem with both installations as long as they were presented and do not interfere with current R&D test at GIF

      • ATL-CSC 5m
        Speaker: Cenk Yildiz (University of California Irvine (US))

        CSC are installed on the side of CMS-GlassRPC ("U2")

        Connected to gas and HV. 

        In the bunker until March/April 2017

         

         

        Hi Roberto,

        We are planning some more tests with the Atlas CSC chamber in 2017.

        We will be repairing two chambers and want to test them before reinstallation in February or March. Each chamber needs only one or two days close to the source. Will there be time available for this test?
         

        Regards,

        Michael Schernau

         

         

        requested position: on the side of the Glass-RPC rack. To be discussed (after April RPC will probably replace the present rack with larger one).

         

      • AIDA2020-radiocromich film 5m
        Speaker: Francesco Fienga (Universita e INFN, Napoli (IT))

        On-site check next week.

        Installation postponed. Setup not ready.

      • Irradiation of optical fiber Belle II - PID 5m

        installation scheduled for November 17 or 24

        Speaker: Ezio Torassa (Universita e INFN, Padova (IT))

        Installation completed yesterday.

        Remove next wednesday

         

        Installation:

        preparation Wednesday November 16. Tentative installation for Wednesday evening (about 6-7 pm)

        In case not completed, 1 more hour on Thursday pm (2pm).

    • 09:30 → 09:40
      Material door: EN proposal 10m

      ATL-MM and CMS-RPC express concern about size of detector+support structure given the fact that the beam is already at 1.6 m.

      ATL-MM and CMS-RPC should send some drawing of  detector+support structure to understand if there is any height conflict with the door.

    • 09:40 → 09:55
      Future Upgrades to the Facility - DT part 15m

      A chance to suggest improvements to to area / control system / etc

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Planning Calendar :

       

      You can subscribe to the calendar with the following link (to be added in you calendar application)

      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

    • 09:55 → 10:30
      Announcements 35m

      1) Maintenance of the irradiator: end of March - 3 days. Nobody see problems/conflicts

      2) Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator

      3) Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted)

      4) INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm) 

       

       

      • INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm) 5m
      • Gas supply during Xmas closure 5m

        gas supply will be closed on Friday December 15 until January 9.

      • Maintenance of the crane: Jan 5 to Jan 18 5m

        no possibility to open bunker during this period.

      • Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted) 5m

        or during maintenance of the irradiator (end of march)

      • Maintenance of the irradiator: end of March - 3 days. 5m
      • Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator 5m