GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Martin Richard Jaekel (CERN), Roberto Guida (CERN)
    • 09:00 → 09:10
      Plan for next wednesday (MD) / thursday (source scan) 10m

      Thursday 24th

      Filter Scan :
      --------------------

      1 ) EP-DT- 13h30 - 14h30
      2)  ATLAS-MM 14h30-18h,
      3) CMS-CSC: 18h-24h

      Short access (10min) to bunker request at 14h30 by CMS-RPC.


      Next Wed Nov 30 : Request to open bunker from Henso

    • 09:10 → 09:30
      Iteration of new requests for tests at GIF 20m

      introduction, goal of the test, plan, needs

      Proposals discussed.

      Everybody confirmed to not see any problem with both installations as long as they were presented and do not interfere with current R&D test at GIF

      • ATL-CSC 5m
        Speaker: Cenk Yildiz (University of California Irvine (US))

        CSC are installed on the side of CMS-GlassRPC ("U2")

        Connected to gas and HV. 

        In the bunker until March/April 2017

         

         

        Hi Roberto,

        We are planning some more tests with the Atlas CSC chamber in 2017.

        We will be repairing two chambers and want to test them before reinstallation in February or March. Each chamber needs only one or two days close to the source. Will there be time available for this test?
         

        Regards,

        Michael Schernau

         

         

        requested position: on the side of the Glass-RPC rack. To be discussed (after April RPC will probably replace the present rack with larger one).

         

      • AIDA2020-radiocromich film 5m
        Speaker: Francesco Fienga (Universita e INFN, Napoli (IT))

        On-site check next week.

        Installation postponed. Setup not ready.

      • Irradiation of optical fiber Belle II - PID 5m

        installation scheduled for November 17 or 24

        Speaker: Ezio Torassa (Universita e INFN, Padova (IT))

        Irradiation complete, samples already removed yesterday.
        Some questions for the RADMON sensors data and how to interpret them.
        We will investigate what data has been given by DT.



         

      • GEM1 and GEM2 setups installation 5m
        Speaker: Lisa Borgonovi (Universita e INFN, Bologna (IT))

        Preferred installation : Closest Position downstream.

        Looks feasible. Meeting on site (Bunker) next Wednesday to define the space organisation.

         

    • 09:30 → 09:40
      Material door: EN proposal 10m

      ATL-MM and CMS-RPC express concern about size of detector+support structure given the fact that the beam is already at 1.6 m.

      ATL-MM and CMS-RPC should send some drawing of  detector+support structure to understand if there is any height conflict with the door.

       

      Drawings received. Martin will re-discuss with EN possible door sizes.

    • 09:40 → 09:55
      Future Upgrades to the Facility - DT part 15m

      A chance to suggest improvements to to area / control system / etc

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      You can subscribe to the calendar with the following link (to be added in you calendar application)http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      Last weeks request :

      • Phone coverage inside bunker.  - Investigation ongoing
      • Area labels for all areas - DONE

      Ongoing Projects :

      • Upgrade of GIF Control System - Online View (Web)
      • Update of DIP publications : NEW path available, old path to be removed after Winter Closure
      • Update of GIF Web Page

      New request :

      • Hardware Signals for source on/off & filter change.
      • Update of Elog to change "Subject" of mails send
      • Automatic entry of Irradiator on/off + filter settings (?)
      • Heartbeat for DIP publications
    • 09:55 → 10:30
      Announcements & AOB 35m

      1) Maintenance of the irradiator: end of March - 3 days. Nobody see problems/conflicts

      2) Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator

      3) Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted)

      4) INFN-AIDA film: Friday 18th. Probably GIF off during morning (9am-2pm) 

       

       

      • INFN-AIDA film - last Friday. Feedback ? 5m
      • Gas supply during Xmas closure 5m

        Gas supply will be closed on Friday December 16 until January 9 !

      • Maintenance of the crane: Jan 5 to Jan 18 5m

        no possibility to open bunker during this period.

      • Installation of upstream XTDV table: requested to install first week 2017 (possibly while waiting for gas supply/detection to be restarted) 5m

        or during maintenance of the irradiator (end of march)

      • Maintenance of the irradiator: Week 13 2017 (27-30.03) 5m
      • Commissioning of the gas detection: last part of EYETS - 1 week "full" stop of GIF. Proposed to join with maintenance of the irradiator 5m
    • 10:30 → 10:50