Notes from BI ELENA meeting
- Updated commissioning schedule (20-Oct-2016) (Gerard T.):
- H-/proton source beam commissioning expected from week #46
- No beam from AD before early 2017
- General remarks: ELENA ‘vistar’ would be very useful (request to C. Carli and OP)
- Individual system status
Orbit system (L. Soby, Diogo):
- VXS crate with CPU and timing connected and powered
- ADC/DSP electronics expected to be installed from next week (Ricardo)
- Front-end software (LNR.BPM device) expected to be clone of AD system (Diogo)
- Turn-by-turn firmware will not be done by RF – need people in BI/PI (L. Soby)
- Expert software tools for first commissioning (new GUIs being designed) (Diogo)
- Likely no valid measurements before beam is bunched from RF
- Local timing configuration being prepared (Diogo)
- Worries about how to handle coasting beam (non-cycling) (Diogo/Ricardo)
- OP tool (YASP) to be configured for ELENA by early 2017 (Diogo/Jorg)
Circulating Scraper/profile (Pierre G.):
- Crate installed in new position due to cabling issues
- No ELENA timing available here (request made for new fibre + BE/CO) (Pierre/Alexandre)
- MCPs to be tested next week
- FESA3 Software testing on-going in lab (need timing for in-situ testing)
KEK Micro-wire SEMs (Gerard T.):
- At least one detector with read-out required for 2016 (SEM #1)
- Problematic electronics with no specifications – what next? (Gerard)
BTVs (Stephane B.):
- Detectors installed (LNI * 1, LNR *2)
- LNR devices on ELENA injection timing – will be done 02/11/2016
Tune (Marek):
- Infrastructure missing (Ethernet, timing and 220 power) in the rack (ground floor)
- Solutions to be found in the coming days (Marek with EN/EL and BE/CO)
- Software (BQSB) will be clone of AD tune server
- OP application (P. Freyermuth) expected to be used (Diogo/Stephen)