GIF++ installation and schedule meeting
-
-
09:00
→
09:15
Plan for next wednesday (MD) / thursday (source scan) 15m
Access requests :
---------------------
Bunker door opening possible - Requests for next week ?Exceptional : VIP Visit today 15h15
- Irradiator OFF for ≈ 30 minutes
- need to turn off HV ?Max : 5 minutes after the Visit, 2-3h later for 5 minutes (to be convirmened)
Source Scan @ Thursday :
-------------------
Filter Scan this week : CSC Downstream : 10h-14h
DT - 30 minutesSource Scan @ next Thursday :
-------------------
-
09:15
→
09:30
Iteration of new requests for tests at GIF 15m
introduction, goal of the test, plan, needs
-
GEM1 and GEM 2 installation 5mSpeakers: Ilaria Vai (Universita e INFN, Pavia (IT)), Lisa Borgonovi (Universita e INFN, Bologna (IT))
-
BLM Reception & Calibration 5m
We need ~one- 1.5 working weeks (during working hours, 8-17) for reception and calibration test of new 830 beam loss monitors. - Second half of May
Speaker: Slava Grishin (Joint Institute for Nuclear Research (RU)) -
RE21 (CBM/FAIR) 5m
MWPC prototypes with up to 16 ASICs will be tested under gamma irradiation using the muon beam as reference signal.
Speaker: Dr Walter Mueller (GSI / FAIR)
-
-
09:30
→
09:40
Beam Schedule 2017 10m
Version 1.0 of the SPS North Area schedule released
-
09:45
→
09:50
Temperature at GIF 5m
Status / Plans / Interventions to address the low temperature problem currently seen inside and outside the bunker area
-
09:50
→
10:05
Future Upgrades to the Facility - DT part 15m
A chance to suggest improvements to to area / control system / etc
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Ongoing Projects :
- Upgrade of GIF Control System - Initial list submitted to DT controls group
- Phone coverage inside bunker. - Fixed Phone mounted in main area. To be active soon.
Web Page :
- Update of GIF Web Page live - please provided feedback and suggestions.
- Please providing publications !
New request :
- Check Temperature ! - Not clear yet, it might be that the AC is nor capable of keeping the temperature stable during the ongoing work in EHN1
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics -
10:05
→
10:30
Announcements 25m
-
IMPACTS for 2017 5m
Guidelines for filling in IMPACT requests
New IMPACT for 2017 ! Please create a new IMPACT (clone the last one).
This will avoid problems with changes made to IMPACT during the last year.Please REVIEW your IMPACT (people, procedures, gas requirements... might have changed)
Proposal : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number. We can provide paper labels.
Attached documents : CAD file (if available, otherwise dimensions). Picture ?
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours.
-
Upcoming Interventions 5m
Scheduled:
---------------12.01.2017 Possible Restart of Irradiation
09.01.2017 Restart of Gas Supply
19.12.2016 17h until March 17, 2017 (!) the entire cooling of the building 887 will be stopped.
05.01-18.01 (+7d) - EHN1 crane unavailable. No opening of bunker area.
27-29.03.2017 Irradiator Maintenance
30.03 - DSO Test
To be scheduled :
----------------------Commissioning of the gas detection - last part of EYETS - 1 week full stop of GIF.
Proposed to join with maintenance of the irradiatorInstallation of upstream XTDV table: 1 week of full stop - waiting for feedback (our proposal was to start 1 week before DSO test)
Bunker door - new door (3.2m high) agreed - waiting for design from EN
Painting of lead bricks - removal and reinstall of all lead bricks (March-April ?)
-
New Announcements 5m
-
AOB 5m
Any Other Business
GAS BILL : please note that the EP-DT budget for GIF does not cover consumables.
Gas used at the GIF++ will have to be paid by the consumer. We will start the TIDs now.FOR NEXT YEAR : Operational budget for the GIF has been reduced by ≈ 20%
Bottles : To replace the missing one.
ATLAS :PATROL RIGHTS H4 :
-----------------------------
We have many people who confuse access to the bunker with the right to patrol the (entire !) beam-line.
Therefore EN gets a high number of requests for H4-Patrol, but prefer only a few people to be able to do it.
They will now REJECT any request that has not been signed by us first.So if you need patrol rights (renewed) please forward the request first to me for signature.
Then it should go through. If not, contact me I will follow it up.
-
-