M. Hori (ELENA beam profile)
- 12 beam profile monitors expected during LS2 (majority for lines to experiments)
- Reliability issue with 100-pin vacuum feed-through. New version to be tested (vacuum)
- BI (Rhodri/Gerard) to launch discussion with M. Hori about:
- Firmware development
- Electronics assembly
- Test bench
- BI software efforts to be planned once VME electronics is documented
Injector BLM (Christos)
- Firmware and software from DAB to VFC during LS2
- Future of ACEM detectors (PSB and PS rings) dismantled before LS2?
- PS transfer-lines and SPS systems to be planned between now and LS2.
- VFC based acquisition to be tested in the PS complex in parallel to OASIS (LN4->PSB)
PS BGI (James)
- Vacuum performance of detector very good so far (~1E-10 mbar steady-state)
- Changes to electronics as bandwidth not sufficient
- Replace detector during YETS (a few decisions to be made still)
- Plans for final read-out electronics to be made (evaluation boards)